How-to

Work in a scenario

Create a branch, edit it freely, and compare it with the organization before anyone decides.

Create

  1. On Design Studio, open New scenario beside the tabs at the top, give it a name and choose Create scenario.
  2. The scenario is now in view: its tab at the top is chosen, and every edit you make goes into it.

Publish in waves

A draft is published in steps: its Waves, each a name and the day it is published. A draft opens with one wave, “Wave 1”, on today. Under Waves, Add a wave gives it another day; Change renames a wave, changes its day (its changes move with it, if the draft still fits on the new day), or removes one with no changes. A change is in the wave of its effective date, and the latest changes say which. Choose the wave the changes go into above the view: on the boxes, in the table, the matrix and the other views, and in the panel, an edit takes its wave's day. When a later wave changes the same thing again (a name, a field, where a unit sits, or removes it), both are kept and the earlier wave says so: from the later day, the later change holds.

Scheduled

  • Schedule adds the waves of today at once; each later wave is added to the organization on its day, and the scenario is applied with its last wave. Whoever opened it is told it was applied, as when a person applies it.
  • Until then Withdraw takes it back to a draft: what is added stays added, the rest can be changed and scheduled again after review.
  • A wave that no longer fits the organization on its day is not added, and neither are the waves after it. The wave says why, and the owners, the admins and whoever opened the scenario are told under Notices and by email.
  • The same happens when the person who scheduled it can no longer act for the organization: withdraw it and schedule it again as an owner or admin.

Design and compare

  • Edit as you would the organization. Compare with where it began marks what the scenario adds, changes or moves: on the boxes and the tree, and in the table, the matrix, the network and the map, where what it removes stays faded in the table and the matrix. Compare with the wave before shows what one wave changes. Each is a switch: turned off, the comparison ends.
  • The scenario's section beside the boxes counts what it adds, removes and changes.

Go back and forth

At the top of Design Studio, after the organization's name, The organization and every scenario that is still running are tabs, each with its name, its status and how many changes of the organization it has not seen. Press a tab to open it. Earlier scenarios lists the scenarios that were applied. Nothing in a scenario is visible in the organization until it is applied, or, for a scheduled one, until its wave's day. The scenario in view stays in view from one screen to the next.

From any screen

  • The organization itself is read, not changed: its lists, Design Studio and Relations offer Change in a draft in place of their forms.
  • On Units, Roles, Positions, People and the other lists, Change in a draft takes you into the organization's open draft, or into a new one named after today when there is none or several, and back to the same page.
  • When nobody else in the organization can approve, Apply now approves the draft and adds it to the organization in one step. The record keeps both steps.